Saturday, September 19, 2015

Sept 16: Drilling the piers for the house

Monday, 9/14/2015

A couple of days after a rain we'd hoped would never materialize (but it did), the pier drilling rig which had been scheduled well in advance to arrive early in the morning, did indeed arrive. The path through which the rig would have to descend and  traverse seemed essentially dry. It appeared the drilling rig would still be able to gain access to the site and get the job done. Descend it did...unfortunately, sinking deeply into the clay where it became increasingly engulfed. The rig ultimately had to be extricated using a large track hoe.

Attempting to get drilling rig down into the work site

Drilling rig stuck nearly up to the axles...it dug in deeper before it was rescued.

Video showing only one portion of the process during which the track hoe removed the drilling rig from the work site.

Wednesday, 9/16/2015

Two days later, after much of the clay had been physically replaced by dryer clay and then allowed to dry further, the drilling rig returned and was successfully able to gain access to the area where the drilling of the piers was to be done. This time the drilling was successful. Rebar cages were introduced into each of the holes and, ultimately, each hole was filled to a designated level with concrete. Next Monday (21 September 2015) begins the work on the footers in the lower area, followed by foundation walls and then onward.

The drilling operation can be seen...but with an assessment along the way in which the operators determine by how far the auger has pierced through any given limestone shelf. In order to establish optimum stability, once through the limestone shelf the drilling was to continue another 5 to 6 feet.

Measuring the level of the concrete in relation to the defined grade.

The majority of the pier holes, after having rebar cages introduced into them, were filled with concrete only up to a specific level well below established grade, as can be seen above.

For the four minor piers which will only have to be able to support portions of the decks, they're brought above grade and can function properly,

A panorama shot of the work site as seen from the west, following the drilling and filling of the piers.

The overall work site as seen from the south.

Tuesday, September 15, 2015

Feb 22-24, 2015: Keith's walk through the destroyed house

The first video will show you the walk starting in the living room and into the bedroom and looking outside. Even now when we see it, we wonder how we survived and are shocked.




This one shows the master bath where he was in the shower with the big glass doors. In the video, you see the wall between the garage and bath was completely blown apart, the back wall on the shower is blown out onto the deck, the ceiling is down, the water heater is in the bathroom now instead of in its closet in the garage. He got through this space with no clothes and no shoes through the broken glass, nails and debris.


 Here's another of the shower area where the brownish tiles are:





Monday, September 14, 2015

sept 13: view of contractors' electric service

Just finished...

Sept 13: mud from big rains...monday pier drilling....

Still muddy





Sept 3: removing another tree where the back wall will be

A few pictures showing the progress...









Sept 2: markings on ground

I forgot to tell you the other day that we found different colored signs on the ground pointing towards the excavation site last week. Red, orange and yellow, each saying OK. I didn't know if you'd seen this or not.










Aug 26: Just after 6 month anniversary of blast


6 months ago this past week, Keith cleaned off the roof of our house after a big wet snow fell and within a few hours, our house was destroyed by the gas explosion. Whenever I see this picture, I sigh. It was a wonderful place to live but not without a huge TO DO list. Yesterday, the contractor, folks drawing the final plans and Keith Farley placed the back wall of the new house in the site. Never did we think any of this could happen in our life time. We are incredibly lucky to have made it out alive with our health, our cats, and much of our artwork. Our new home will not have the pool you see beyond the deck rail, but it will be situated in the landscape to have the best views of the woods and land. Timothy West designed the new house and gave it his loving care to use the spaces to bring what was wonderful in the old house into the new house.


before

after